Hunter Valley Capacity Expansion program, circa $1.6B – building from 115MTpa in 2011 to 270MT pa by 2016
The Project Team, employed on client side (prior to establishing EJC Projects) led the various Heavy Haul Rail Projects supporting the HV Coal Industry (30T axle load) across the Hunter Valley (35 in total), including;
- Maitland to Minimbah 3rd Road ($363m);
- New Loops and extensions from Muswellbrook to Narrabri ($160m);
- 9 New Passing Loops on the Ulan Line ($130m);
- Nundah Bank 3rd Road ($80M);
- Antiene to Grasstree Duplication ($45M); and
- Drayton and Newdell Junctions ($40M)
The EJC Team included General Manager, Project Director, Project Managers, Contract Specialists and Site Supervisors.
The Project Team, employed on client side (prior to establishing EJC Projects) led the various Heavy Haul Rail Projects supporting the HV Coal Industry (30T axle load) across the Hunter Valley (35 in total), including;
- Maitland to Minimbah 3rd Road ($363m);
- New Loops and extensions from Muswellbrook to Narrabri ($160m);
- 9 New Passing Loops on the Ulan Line ($130m);
- Nundah Bank 3rd Road ($80M);
- Antiene to Grasstree Duplication ($45M); and
- Drayton and Newdell Junctions ($40M)
The EJC Team included General Manager, Project Director, Project Managers, Contract Specialists and Site Supervisors.